Schedule
When should the work happen?Logic-linked activities establish the construction sequence and completion milestones.
Residential construction · Primavera P6
I developed an integrated construction programme covering schedule logic, procurement, resources, costs, baseline management, progress updating and variance analysis.
Explore case study ↓I translated the project lifecycle into a structured Work Breakdown Structure, then defined activities, durations, milestones and logic. The objective was not simply to draw a Gantt chart, but to create a programme that could operate as a project-control tool.
Predecessor relationships reflect the construction method and connect procurement to installation. This makes critical-path and float analysis meaningful.
“The schedule was driven by logic and dependencies—not simply by entering start and finish dates.”
03 / Procurement integration
Engineering approvals and long-lead procurement were integrated with construction activities so the programme reflected real delivery constraints.
The approved plan was preserved as a baseline. Labour, equipment and material resources were assigned to activities, supporting time-phased costs and meaningful comparison after progress updates.
09 / What the programme tells me
Logic-linked activities establish the construction sequence and completion milestones.
Labour, equipment and materials are connected to the activities that consume them.
Resource and cost loading create a time-phased view of planned project expenditure.
Baseline and variance analysis reveal movement and activities affecting performance.
10 / Project controls workflow
My approach is to treat Primavera P6 as a project-control system, not simply a programme-drawing tool.
11 / Project outcome
The final programme demonstrates my ability to take a construction scope and develop it into a structured controls model—connecting time, resources, cost, progress and variance to support informed decisions.